( 1 ) belt conveyor installation method should be required to install a fixed basis. Before moving belt conveyor officially running wheels should live with a triangular wedge or stopped with the brake . In order to avoid
Work move occurs , a number of parallel conveyor job, between machine and machine , there should be one meter channel between the Grain Conveyors and the wall.
Must be checked before ( 2 ) the use of each conveyor belt moving parts , belt buckle and carrying device is normal , protective equipment are complete . Tension degree before starting the tape shall be adjusted to the appropriate
Degree .
( 3 ) No-load belt conveyor should start . Once it is operating normally before feeding . Prohibited after the first feeding drive.
( 4 ) There are several sets of belt conveyors running in series , the discharge end should start sequence start . After all the normal operation before feeding .
Tape deviation phenomenon ( 5 ) when the operation should stop adjustment shall not reluctant to use in order to avoid frayed edges and increase the load .
( 6 ) working environment and sent the material at a temperature not higher than 50 ℃ and below -10 ℃. Transportation of materials with pH shall oils and organic solvents ingredients.
( 7 ) belt conveyors prohibit pedestrians or people on the ride .
( 8 ) must be stopped before stopping feeding , unloading and other material on the belt to make deposits before parking.
( 9 ) belt conveyor motor must be well insulated . Mobile conveyor cables do not Luanla and dragging. Motor should be grounded.
( 10 ) non- slip hand to pull the belt when the belt in order to avoid accidents.