Bucket Elevator factory is divided into several parts , so refer to the following in accordance with site-specific installation order of the various components shipped to the installation site in advance the appropriate location , depending on the installation master plan , refer to the following requirements for installation :
1 according to the drawings, based on the anchor bolt holes checked .
2 would be fixed on the basis of the lower section and the leveling datum ( the flange ) . On the flange surface and the horizontal parallelism tolerance is 1/1000mm. Adjust the horn must be close to the anchor bolts.
3 chassis and connection box installed, peripheral flange must be neat , there should be significant dislocation. The connection between the housing flange pad into 3mm thick asbestos rope , asbestos rope can be coated with some butter , asbestos rope positioned to facilitate and increase the sealing effect. Mat asbestos rope , first put on the chassis flanges bolts, then bolt the outer perimeter of the flange connection .
4 chassis mounted to a certain height ( according to the technical design ) . Install outdoor ( internal ) fixing bracket, to be securely fixed to the nearest building. Mounting bracket generally an interval of 8 ~ 10m , mounting bracket allow limitations hoist in the vertical direction of the free expansion .
5 If you have non-standard chassis, generally installed in the upper section of the festival under the first position, if you have special requirements, can be installed in a different location.
6 side mounted chassis, while measuring the vertical cabinet .
7 The upper section of the installation, to calibrate the spindle centerline , so that the lower level and with the centerline of the shaft parallel alignment. Upper shaft parallel with the horizontal centerline tolerance is 0.3/1000mm, down axis perpendicular plane with error less than 4mm, the upper and lower rollers face the same vertical plane error is less than 5mm.
8 drives in the elevator factory has been connected with the upper section of the drive spindle is good, and install location, taking into account the vibration during transportation equipment factory , as well as lifting may occur during collisions. Therefore , the upper section