2013年10月9日星期三

Use and maintenance of the screw conveyor points to note are those

Screw conveyor is used for conveying powder , granular, small block materials, general-purpose transportation equipment, all kinds of bearings are in the dust in the work , so the working conditions so reasonable operation and maintenance of the screw conveyor to a more great significance , screw conveyor operation and maintenance of the main requirements are as follows :

    1 , please use the screw conveyor , on normal operating procedures to operate, and often observe the screw conveyor is abnormal condition exists. If there is an abnormality please shut down for inspection, troubleshooting before operation.

    2, please pay attention to safety , do not place your hands or other objects into the rotating parts .

    3 , during use , screw conveyor is strictly prohibited heavy start , start feeding should be preceded by the host , and then feeding ; should be checked before the start of the cylinder body I is too much material .

    4, in order to ensure no load starting screw Fluting machine requirements , conveyor feeding should be stopped before stopping , and other material inside the chassis rear was completely lost all stopped .

    5 , in strict accordance with the mixer loading capacity : no more than the effective volume of the mixer used under strict overload use , it would burn or damage the gear motor and other components . After adding the material must remember not to stop halfway , try to avoid overloading the next start-up.

    6 , the initial feed screw conveyor , the feed rate should be increased gradually until it reaches the conveying capacity , feeding should be uniform, or likely to cause transport of materials product plugs, drive overload .

    7 , the material being transported shall not be mixed with chunks of hard materials to avoid causing death card spiral screw machine damage.

    8 , the normal operation of 1800 hours conveyor should be a small repair , mainly to check lubrication or replacement of wearing parts ;

    9 , the normal operation of 4000 hours should be overhauled , mainly for all assemblies demolition inspection and cleaning, replacement or correction of all wearing parts and standard parts .

    When removing the screw conveyor please remember the clear sequence , while the reverse order when assembled can be combined . The local host helix and direction of rotation of the feed screw should follow the direction signs, strict reverse direction !